Question: Order quantity = 200 units From route sheet Operation Work center Days Setup time (standard hours) Run time (standard hours) Total time (standard hours) 10

Order quantity = 200 units From route sheet Operation Work center Days Setup time (standard hours) Run time (standard hours) Total time (standard hours) 10 8 1.5 0.2 3 20 9 0.5 0.3 4 From work center files Work center Queue (days) Wait (days) Move (days) 8 2 1 1 9 4 1 1 Schedule Operation Wait and Work center Arrival date Queue (days) Operation (days) Finish date move 10 8 2 20 9 2 Store Stores 120 APICS 5.42 APICS Confidential and Proprietary