Question: Order quantity = 200 units From route sheet Operation Work center Days Setup time (standard hours) 1.5 Run time (standard hours) 0.2 Total time (standard

Order quantity = 200 units From route sheet Operation Work center Days Setup time (standard hours) 1.5 Run time (standard hours) 0.2 Total time (standard hours) 10 8 3 3 20 9 0.5 0.3 4 From work center files Work Center Queue (days) Wait (days) Move (days) 8 2 1 1 9 4 1 1 Schedule Operation Work center Arrivai date Queue (days) Operation (days) Finish date Watand move 10 8 2. 20 9 2 Store Stores 120 5.42 APICS Confidential and Proprietary Apics