Question: ou are the project manager on a $ 1 , 0 0 0 , 0 0 0 housing development project that has an estimated duration

ou are the project manager on a $1,000,000 housing development project that has an estimated duration of five month.
You are at the end of month two. According to the project estimate, your team should be done with 40% of the work.
As of today, the project is 45% complete while 50% budget has been used. Show your conclusion about the project performance below. Choose the right options from the drop-down list.
BAC = blank
AC = blank
PV = blank
EV = blank
CPI = blank
SPI = blank
Since CPI is blank , the project is blank budget.
And since SPI is blank , the project is blank of schedule.
$400,000 $1,000,000 $100,000 above 1.50.9 equal to 1 $500,00011.125 ahead less than 1 $450,000 $10,000,000 more than 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!