Question: Our crayon production line has 3 processes for which it uses 3 machines. Machine # 1 takes 4 minutes to work on a batch of

Our crayon production line has 3 processes for which it uses 3 machines. Machine # 1 takes 4 minutes to work on a batch of crayons. Machine # 2 takes 10 minutes. Machine # 3 takes 9 minutes.
What is the Cycle Time of our 2nd batch of crayons?
Our crayon production line has 3 processes for which it uses 3 machines. Machine # 1 takes 4 minutes to work on a batch of crayons. Machine # 2 takes 10 minutes. Machine # 3 takes 9 minutes.
What is the Cycle Time of our 2nd batch of crayons?
9 minutes
60 minutes
23 minutes
10 minutes
Which of the following statements regarding supplier selection is true?
The supplier should be selected on the basis of price only because the cost of materials is a significant portion of the total product cost.
The supplier should be selected only on the basis of the strength of the personal relationships between the supplier and purchasing management teams.
The supplier should be selected primarily on the basis of the shortest lead time because longer lead times increase the cost of inventory.
The supplier should be selected on the basis of quality, good managers, financial stability, price and lead times.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!