Question: Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four

Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.

Activity Cost Activity Base
Procurement $363,400 Number of purchase orders
Scheduling 220,700 Number of production orders
Materials handling 412,500 Number of moves
Product development 784,000 Number of engineering changes
Production 1,578,500 Machine hours
Number of Purchase Orders Number of Production Orders Number of Moves Number of Engineering Changes Machine Hours Number of Units
Disk drives 3,830 430 1,440 12 2,400 1,700
Tape drives 2,000 165 710 7 9,500 3,900
Wire drives 12,900 820 3,600 26 11,000 2,400

The activity-based cost for each disk drive unit is

a.$228.78

b.$769.84

c.$19.4

d.$364.22

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!