Part 3- Case Study in Simulation - KanBan Levels (35 points)
You have a 3 machine simulation. Jobs arrive at a rate of 1 job per minute with exponential arrival times. You have a series of 3 machines. All machines take uniform distribution from .7 to 1 minutes to process a job. Thus, the utilization is 85%(all machines). Set the maximum queue size in front of each machine to 1000,10,5, and 2. Comment on the system performance under low inventory levels.