Question: Part 3 . Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs in a schedule ABCDE is 1 st ,2

Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ]

[Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.]

Five jobs arrived to be processed with the processing times and due dates.

Present Date=

257

Work Order

A

B

C

D

E

Processing Times (Days)

15

6

40

12

8

Due Date

269

266

297

293

264

. . .

Question 3. The FIFO schedule is ABCDE (where job A is the first job) and the LIFO schedule is EDCBA (where job E is the first job).

Consider the schedules based on the sequencing rules: Minimum Processing Time (MPT); Earliest Due Date (EDD); Minimum Slack Time (MST); and Minimum Critical Ratio (MCR). How many of the schedules are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4

The schedule based on the MPT sequencing rule is BEDAC

The schedule based on the EDD sequencing rule is BEADC

The schedule based on the MST sequencing rule is EBADC

The schedule based on the MCR sequencing rule is AECBD

. . .

Question 4. Consider the MPT schedule.

How many statements are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4

Statement 1. The total processing time of the schedule is 81

Statement 2. The total flow of the schedule is 168

Statement 3. The total lateness of the schedule is 90

Statement 4. The Makespan of the schedule is 81

. . .

Question 5. Consider the FIFO schedule.

How many statements are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4

Statement 1. The flow of job B is 21

Statement 2. The lateness of job C is 21

Statement 3. The date of completion of job D is 330

Statement 4. The queue time of job E is 73

. . .

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!