Question: Part 3 . Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs in a schedule ABCDE is 1 st ,2
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ]
[Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.]
Five jobs arrived to be processed with the processing times and due dates.
| Present Date= | 257 |
|
|
|
|
| Work Order | A | B | C | D | E |
| Processing Times (Days) | 15 | 6 | 40 | 12 | 8 |
| Due Date | 269 | 266 | 297 | 293 | 264 |
. . .
| Question 3. The FIFO schedule is ABCDE (where job A is the first job) and the LIFO schedule is EDCBA (where job E is the first job). Consider the schedules based on the sequencing rules: Minimum Processing Time (MPT); Earliest Due Date (EDD); Minimum Slack Time (MST); and Minimum Critical Ratio (MCR). How many of the schedules are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 The schedule based on the MPT sequencing rule is BEDAC The schedule based on the EDD sequencing rule is BEADC The schedule based on the MST sequencing rule is EBADC The schedule based on the MCR sequencing rule is AECBD . . . |
|
|
| Question 4. Consider the MPT schedule. How many statements are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 Statement 1. The total processing time of the schedule is 81 Statement 2. The total flow of the schedule is 168 Statement 3. The total lateness of the schedule is 90 Statement 4. The Makespan of the schedule is 81 . . . |
|
|
| Question 5. Consider the FIFO schedule. How many statements are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 Statement 1. The flow of job B is 21 Statement 2. The lateness of job C is 21 Statement 3. The date of completion of job D is 330 Statement 4. The queue time of job E is 73 . . . |