Question: Part 5 : Earned Value Analysis 1 Given the scenario below, answer questions 4 2 through 4 7 . A task includes laying down 1
Part : Earned Value Analysis
Given the scenario below, answer questions through
A task includes laying down of asphalt. Two teams are working in two shifts, one morning shift, and one evening shift, each hours long Team works AM to PM Team works PM to PM It is estimated that completing this task will take consecutive days. The combined wages of team are $ per hour. The combined wages of team are also $ per hour, however they are paid a premium for every hour worked after : PM
At the end of day of asphalt has been completed, but it should also be noted that Team had actually been working from PM to PM for of the last days.
What is the BAC of this task?
a $
b $
c $
d $
What is the CPI of this task?
a
b
c
d
What is the SPI of this task?
a
b
c
d
Assuming the remainder of the work is to be done according to plan, what is the EAC?
a $
b $
c $
d $
Assuming the remainder of the work is to be done at the current CPI, what is the ETC?
a $
b $
c $
d $
What is the TCPI required from this point onwards, in order to complete this project on budget?
a
b
c
d
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock