Question: Part 6: Based on the data presented in the Unit VII Spreadsheet Template in Excel (Variances tab), complete the following calculations. Calculate the material variances.

Part 6: Based on the data presented in the Unit VII Spreadsheet Template in Excel (Variances tab), complete the following calculations.

  • Calculate the material variances.
  • Calculate the labor variances.

Complete your calculations by filling in the highlighted cells, and embed a copy of the completed spreadsheet into this report. Discuss your observations about the variances and ways to plan to improve any of the variances.

This is a 5301-Magerial Accounting applications course

Cookie Business
Actual Total Cost of Direct Materials $ 225,000
Standard Total Cost of Direct Materials $ 224,800
Actual Materials Used 30
Standard Materials Used 31
Actual Direct Labor Rate $ 15.50
Standard Labor Rate $ 15.00
Actual Hours Worked 45
Standard Hours Worked 40
Amount Favorable/ Unfavorable
Calculate Materials Variances:
Materials Price Variance $ 200 Unfavorable
Materials Quantity Variance $ 7,493 Unfavorable
Calculate Labor Variances:
Labor Rate Variance $ 23 unfavorable
Labor Efficiency Variance $ 75 unfavorable

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!