Question: Part 6: Based on the data presented in the Unit VII Spreadsheet Template in Excel (Variances tab), complete the following calculations. Calculate the material variances.
Part 6: Based on the data presented in the Unit VII Spreadsheet Template in Excel (Variances tab), complete the following calculations.
- Calculate the material variances.
- Calculate the labor variances.
Complete your calculations by filling in the highlighted cells, and embed a copy of the completed spreadsheet into this report. Discuss your observations about the variances and ways to plan to improve any of the variances.
This is a 5301-Magerial Accounting applications course
| Cookie Business | |||
| Actual Total Cost of Direct Materials | $ 225,000 | ||
| Standard Total Cost of Direct Materials | $ 224,800 | ||
| Actual Materials Used | 30 | ||
| Standard Materials Used | 31 | ||
| Actual Direct Labor Rate | $ 15.50 | ||
| Standard Labor Rate | $ 15.00 | ||
| Actual Hours Worked | 45 | ||
| Standard Hours Worked | 40 | ||
| Amount | Favorable/ Unfavorable | ||
| Calculate Materials Variances: | |||
| Materials Price Variance | $ 200 | Unfavorable | |
| Materials Quantity Variance | $ 7,493 | Unfavorable | |
| Calculate Labor Variances: | |||
| Labor Rate Variance | $ 23 | unfavorable | |
| Labor Efficiency Variance | $ 75 | unfavorable | |