Question: PART I - Project Cash Flow Analysis Analyze the cash inflows and outflows of the project shown below following the Example Project Cash Flow Analysis
PART I - Project Cash Flow Analysis
Analyze the cash inflows and outflows of the project shown below following the Example Project Cash Flow Analysis posted in Module 1 lecture resources. What is the contractor's expected profit in this project?
| Work Type | Month 1 | Month 2 | Month 3 | Month 4 | Month 5 |
|---|---|---|---|---|---|
| Move in | 1,750 | ||||
| Survey | 800 | ||||
| Trench | 2,300 | 5,250 | |||
| Lay Pipe (Sub) | 2,250 | ||||
| Concrete (Sub) | 700 | 700 | |||
| Backfill | 500 | ||||
| Move out | 350 | ||||
| Fix Valves | 700 | ||||
| Put Valves | 700 | ||||
| Test | 1,000 |
- The dollar values shown in the table above are in thousands
- The contractor is subcontracting the pipe laying and concreting works only.
- The owner and engineer need one month to review, approve, and authorize progress payment upon receipt of the invoice from the contractor.
- The contractor will pay the subcontractors the same month he collects his payment from the owner.
- The contractor's total indirect costs are $1,800,000 and the markup is 3%.
- The retainage percent is 10%.
- Use an interest rate of 1.5%.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock