Question: PART I - Project Cash Flow Analysis Analyze the cash inflows and outflows of the project shown below following the Example Project Cash Flow Analysis

PART I - Project Cash Flow Analysis

Analyze the cash inflows and outflows of the project shown below following the Example Project Cash Flow Analysis posted in Module 1 lecture resources. What is the contractor's expected profit in this project?

Work Type Month 1 Month 2 Month 3 Month 4 Month 5
Move in 1,750
Survey 800
Trench 2,300 5,250
Lay Pipe (Sub) 2,250
Concrete (Sub) 700 700
Backfill 500
Move out 350
Fix Valves 700
Put Valves 700
Test 1,000
  • The dollar values shown in the table above are in thousands
  • The contractor is subcontracting the pipe laying and concreting works only.
  • The owner and engineer need one month to review, approve, and authorize progress payment upon receipt of the invoice from the contractor.
  • The contractor will pay the subcontractors the same month he collects his payment from the owner.
  • The contractor's total indirect costs are $1,800,000 and the markup is 3%.
  • The retainage percent is 10%.
  • Use an interest rate of 1.5%.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!