Question: Part X requires machining on a milling machine ( operations A and B are required ) . Find the number of machines required to produce

Part X requires machining on a milling machine (operations A and B are required).Find the number of machines required to produce 3000 parts per week. Assume thecompany will be operating five days per week, 18 hours per day. The following information is known:Operation A Standard Time 3 min Efficiency 95% Reliability 95% Defect Rate2%B 5 min 95%90%5%Note: The milling machine requires tool changes and preventive maintenance afterevery lot of 500 parts. These changes require 30 minutes.