Question: Path probabilities are calculated by dividing path mean by path standard deviations. True False Question 9 1 pts The earliest finish time for an activity
Path probabilities are calculated by dividing path mean by path standard deviations.
True
False
Question
pts
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.
True
False