Question: Patrick just finished designing a process improvement plan. To ensure that it is going to be successful, he embedded a step in the plan for

Patrick just finished designing a process improvement plan. To ensure that it is going to be successful, he embedded a step in the plan for a designated staff member to periodically verify that the finished products remain compliant to specifications. Which deliverable is this considered? New process integration Control verification Monitor and control plan Procedures and training