Paul is scheduled to work on a critical project task originally quoted a cost of $20,000 with a duration of 7 days. Eager to speed up the project, Company requested a quote for the fastest which Paul could complete the task. Paul has just replied with a "fastest" quote for the project task of 4 days for a cost of $32,000. Assuming a linear relationship between cost and duration of the original quote and the "fastest quote, what would you expect the task to cost of you wanted it completed in 5 days?