Question: Payment scheduling and PERT Problem 2 ( 3 5 pts ) Consider the project information below. Assume that the overhead cost of the project is

Payment scheduling and PERT Problem 2(35 pts) Consider the project information below. Assume that the overhead cost of the project is $75 per unit time. a) What is the optimal project duration that will minimize the sum of direct and indirect costs and what is the total cost of this project? (15 points) b) The following payment schedule is associated with some events (nodes). The interest rate is 15%(r =0.15). Find the optimal payment schedule for this project. (20 points)
Event PartialPayment
4 $1,000
5 $3,500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!