Question: PB #1 End item A has a planned lead time of 2 weeks. There are currently (Week 0) 120 units on hand. Compute the planned

PB #1 End item A has a planned lead time of 2
PB #1 End item A has a planned lead time of 2 weeks. There are currently (Week 0) 120 units on hand. Compute the planned order releases using lot-for-lot for the MPS shown here: Week 2 8. 10 84 Demand 30 49 18 86 42 84 44 41 PB #2 (a) Rework Problem 1 with 40 units of safety stock. (b) Rework Problem 1 with 50 units of safety stock

Step by Step Solution

There are 3 Steps involved in it