Question: Perform a cost variance analysis and calculate the project progress by cost and the estimated project cost at completion if past cost performance is expected

Perform a cost variance analysis and calculate the project progress by cost and the estimated project cost at completion if past cost performance is expected to continue.
Control
Account
Estimated
Cost (EP)
Percent
Complete
Actual
Cost (EP)
200,000
100
205,000
D
90,000
60
50,000
50,000
25
23,000
CB
200,000
26
44,000