Question: Perform the Critical Path Method (CPM) analysis for the project. From the information in Table 2, draw the CPM network and calculate the free float
- Perform the Critical Path Method (CPM) analysis for the project. From the information in Table 2, draw the CPM network and calculate the free float if available. The project has 9 activities and has to be completed in 24 months. Decide the duration (in month) for each of the activities.
Table 2/Jadual 2
| ID | Activity/Aktiviti | Preceeding Activity (IPA) / Aktiviti Mendahului | Duration/Tempoh (month/bulan) |
| A | Site clearing | - | |
| B | Mobilization | A | |
| C | Earthwork | B | |
| D | Piling | C | |
| E | Foundation | D | |
| F | Superstructure | E | |
| G | Architecture Finishing | F | |
| H | M&E work | F | |
| I | Commissioning | G, H |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock