Question: Perform the Critical Path Method (CPM) analysis for the project. From the information in Table 2, draw the CPM network and calculate the free float

  1. Perform the Critical Path Method (CPM) analysis for the project. From the information in Table 2, draw the CPM network and calculate the free float if available. The project has 9 activities and has to be completed in 24 months. Decide the duration (in month) for each of the activities.

Table 2/Jadual 2

ID Activity/Aktiviti

Preceeding Activity (IPA) /

Aktiviti Mendahului

Duration/Tempoh (month/bulan)
A Site clearing -
B Mobilization A
C Earthwork B
D Piling C
E Foundation D
F Superstructure E
G Architecture Finishing F
H M&E work F
I Commissioning G, H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!