Question: PERT Activity Name Predecessor Optimistic Pessimistic Likely A 4 6 8 B A 5 7 15 C A 4 8 12 D B 15 20
PERT
| Activity Name | Predecessor | Optimistic | Pessimistic | Likely |
| A |
| 4 | 6 | 8 |
| B | A | 5 | 7 | 15 |
| C | A | 4 | 8 | 12 |
| D | B | 15 | 20 | 25 |
| E | B | 10 | 18 | 26 |
| F | C | 8 | 9 | 16 |
| G | E | 4 | 8 | 12 |
| H | D, F | 1 | 2 | 3 |
| I | G, H | 6 | 7 | 8 |
According to the above table,
- Find the critical Path
- Calculate the total project duration
- Calculate Project variance and standard deviation
- What is the probability of completion in 55 days
- What is the completion of the project with 0.90 chance