Question: 3) Use the values below in the table to undertake the following: a) Calculate the activity durations. b) Draw the network diagramme. c) Which path


3) Use the values below in the table to undertake the following: a) Calculate the activity durations. b) Draw the network diagramme. c) Which path is critical? Please, justify your response. d) How closely should the other path be watched and why? Activity Predecessor Optimistic Likely Pessimistic A 4 6 B A 2 5 7 10 8 9 A B 9 D E F 6 3 7 7 9 D,E 20 11 19 11 4) Construct a network using the information in the table and identify the critical path. Predecessor Time 4 6 16 Activity A B D E 19 11 16 A B B, C D E, F G F 4 G 8 H 17 7
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
