Question: Pipe Installation Project Activity A: Dig trench for 1.2km and takes 6 days to complete. Activity B: Lay pipe for 1.2km and takes 6 days

Pipe Installation Project Activity A: Dig trench
Pipe Installation Project Activity A: Dig trench for 1.2km and takes 6 days to complete. Activity B: Lay pipe for 1.2km and takes 6 days to complete. Activity C: Refill earth for 1.2km and takes 6 days to complete. 4. Using Finish to Start relationship for the above activities, how long the project will take? (1 mark) 5. Using Laddering techniques and divided each activity to 3 segments equally. i. How long the project will take? (2 marks) ii. How many Lag days between activity A and B? (2 marks) : Page 2 of 2