A) based on the activity time estimates, the expected times AND variance for each of the activities are ?? (For activities A through D)
B) the expected completion time of the critical path = ?? Weeks.
The expected completion time of the path other than the critical path = ?? Weeks.
C) the variance of the critical path = ?? Weeks.
The variance of the path other than the critical path = ?? Weeks.
D) if the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 22 weeks or less = ??
E) D) if the time to complete the activities on the NON - critical path is normally distributed, then the probability that the critical path will be finished in 22 weeks or less = ??