Question: Please answer all questions. 1) For any complex project, once the project stakeholders are identified, the next step is to classify these stakeholders based on
Please answer all questions.
1) For any complex project, once the project stakeholders are identified, the next step is to classify these stakeholders based on their current and desired engagement levels. What is the benefit of classifying the project stakeholders?
Group of answer choices
To help populate the stakeholder register.
It is a mandatory step in stakeholder analysis.
To help define an approach strategy.
To help identify the project scope.
2)
Peter is managing a multimillion-dollar project. The project is in the planning phase and has a big number of key stakeholders. During an analysis, Peter finds out that there are big gaps between the current and desired engagement levels for most of the key stakeholders. What should Peter do next?
Group of answer choices
Brainstorm on the stakeholder management strategies that can close these gaps.
Prepare a business case for the project.
Immediately escalate the situation to the project sponsor.
Propose to terminate the project.
3) The Identify Stakeholders process is an initiating process. At this stage, which of the following organizational process assets is the most crucial input to this process?
Group of answer choices
Risk control procedures
Change control procedures
Lessons learned from previous projects
Financial control procedures
4) Which of the following should be done FIRST during the Project Life Cycle?
Group of answer choices
Select and quantify the stakeholder interests and expectations for the project.
Identify the key people and organizations that have a stake in the project.
List the key people and organizations that have a stake in the project.
Ascertain the stakeholder interests and expectations for the project.