Question: Please answer all the questions in this quiz based on the below project information: Task Predecessor Time (days) Crash Cost (per day) Maximum Allowable Crash

Please answer all the questions in this quiz based on the below project information:

Task Predecessor Time (days) Crash Cost (per day) Maximum Allowable Crash Days
A - 6 Cannot Crash Does not apply
B A 1 Cannot Crash Does not apply
C A 3 Cannot Crash Does not apply
D B,C 7 Cannot Crash Does not apply
E D 8 Cannot Crash Does not apply
F E 1 Cannot Crash Does not apply
G E 2 $400 1
H E 3 $120 2
I F 2 $240 1
J G 4 $240 2
K H 7 $75 3
L I 4 $190 2
M J 9 $270 5
N K 4 $100 2
O L,M,N 14 $300 8

1. What is the critical path of the project?

2. will Delaying Task D will always delay the project.

3. will Delaying Task F by more than 20 days will always delay the project?

4.What is the project length in days (assume no delays)?

5. What is the slack (in days) for task F?

6. What is the slack (in days) for task G?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!