Question: Please answer all the questions in this quiz based on the below project information: Task Predecessor Time (days) Crash Cost (per day) Maximum Allowable Crash
Please answer all the questions in this quiz based on the below project information:
| Task | Predecessor | Time (days) | Crash Cost (per day) | Maximum Allowable Crash Days |
| A | - | 6 | Cannot Crash | Does not apply |
| B | A | 1 | Cannot Crash | Does not apply |
| C | A | 3 | Cannot Crash | Does not apply |
| D | B,C | 7 | Cannot Crash | Does not apply |
| E | D | 8 | Cannot Crash | Does not apply |
| F | E | 1 | Cannot Crash | Does not apply |
| G | E | 2 | $400 | 1 |
| H | E | 3 | $120 | 2 |
| I | F | 2 | $240 | 1 |
| J | G | 4 | $240 | 2 |
| K | H | 7 | $75 | 3 |
| L | I | 4 | $190 | 2 |
| M | J | 9 | $270 | 5 |
| N | K | 4 | $100 | 2 |
| O | L,M,N | 14 | $300 | 8 |
1. What is the critical path of the project?
2. will Delaying Task D will always delay the project.
3. will Delaying Task F by more than 20 days will always delay the project?
4.What is the project length in days (assume no delays)?
5. What is the slack (in days) for task F?
6. What is the slack (in days) for task G?