Question: Please Answer and show work neatly for a better understanding Thank you A project consists of three tasks. Task A is scheduled to begin at
Please Answer and show work neatly for a better understanding Thank you

A project consists of three tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 3. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to being at the start of Week 2 and end at the end of Week 3 . The budgeted cost for Task A is $25,000, for B is $18,000 and for Task C is $16,000. At the end of the second week, Task A is 50% complete, Task B is 80% complete, and Task C is 70% complete. What is the SPI for the project at the end of the second week? Also indicate whether it is ahead or behind schedule. 0.94