Question: Please answer each part of this question in relation to the completed chart. A PERT chart consists of three separate paths of activities connecting the
Please answer each part of this question in relation to the completed chart.
A PERT chart consists of three separate paths of activities connecting the starting point with the ending point with the indicated time to completion for each path. Fill in the table
|
Path | Time to Complete in Months | Critical Path Yes/No |
Slack |
| A | 10 | yes | 0 |
| B | 7 | no | 3 |
| C | 9 | no | 1 |
Please answer 1. the time to complete the project if the following occurred
Please answer 2. what does this mean to you as project manager responsible for getting the job done on time? Treat each separately. Start with Path B taking 7 months.
Path B is going to be delayed by 1 month.
1.
2.
Path B is going to be delayed by 2 months.
1.
2.
Path B is going to be delayed by 3 months.
1.
2.
Path B is going to be delayed by 4 months.
1.
2.