Question: Please answer only if you know.P6 Primavera Question: for this activity, how to make early start date as 09/12/19? Why does it affect the schedule
Please answer only if you know.P6 Primavera Question: for this activity, how to make early start date as 09/12/19? Why does it affect the schedule when there is no free or total floats. It is changing and taking its date as the data date. It should get the project start date, not the data date, because this is the first activity of the project.