Question: Please answer the following question with the complete steps: 2/ Draw the network and identify the critical path. Also calculate the ES, EF, LS, and
Please answer the following question with the complete steps:

2/ Draw the network and identify the critical path. Also calculate the ES, EF, LS, and LF for each activity. Activity Preceding Activity Time (weeks) A - 4 B - 6 C A, B 7 D B 8 E B 5 F C 5 G D 7 H D, E 8 I F, G, H 4