Question: Please answer the following questions and keep one decimal place after dot in your results.1. Calculate the expected time and standard deviation of each activitys
Please answer the following questions and keep one decimal place after dot in your results.1. Calculate the expected time and standard deviation of each activitys duration.(Fill in the table above.)2. Create a project network (AON) from the table above and identify the critical path. (Hint: You do not have to use the forward pass and backward pass. It suffices to visually identify all possibly paths from start to end and then identify the path with the longest duration.)3. Whats the expected project completion time?4. Whats the standard deviation of the project completion time?5. What is the project due date that can be met with 95% probability? (Hint: )