Question: PLEASE ANSWER THE FOLLOWING QUESTIONS - USING TABLE 7.9, WHAT IS THE EARLIEST COMPLETION TIME OF THIS PROJECT IF NORMAL TIMES ARE USED FOR ALL

PLEASE ANSWER THE FOLLOWING QUESTIONS -
USING TABLE 7.9, WHAT IS THE EARLIEST COMPLETION TIME OF THIS PROJECT IF NORMAL TIMES ARE USED FOR ALL ACTIVITIES?
USING TABLE 7.9, WHAT IS THE MINIMUM TIME SCHEDULE FOR THIS PROJECT?
Question 16 1 pts Table 7.9 TIME (WEEKS) NORMAL CRASH COST (S) NORMAL CRASH ACTIVITY IMMEDIATE PREDECESSOR(S) 3,300 A B 3 6 1 2 4 1 3,000 8.000 4,000 9,000 A 4,000 D E F A B 5 4 2 4 3 2 3,500 4,750 2.000 4,000 5,500 2.000 G H I J D DF E,G E 1 3 3 2 1 2 2 1 4,000 3,500 3,000 5,000 4,000 3,750 4,250 7,000 Using Table 7.9, what is the earliest completion time of this project if normal times are used for all activities? O more than 14 weeks 14 weeks fewer than 13 weeks O 13 weeksStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
