Question: Please answer these simple project calculations End of week 10 $83,000 was budgeted $86 was actually expended $73,000 was the earned value of work actually
Please answer these simple project calculations
End of week 10
$83,000 was budgeted
$86 was actually expended
$73,000 was the earned value of work actually performed
1. Calculated the Project cost performance index?
2. Calculate the Project cost Variance?