Question: Please create a network diagram through MS Visio with early start, early finish, late start, late finish, duration, and slack with the given data: begin{tabular}{|c|c|c|c|c|c|}
Please create a network diagram through MS Visio with early start, early finish, late start, late finish, duration, and slack with the given data:


\begin{tabular}{|c|c|c|c|c|c|} \hline & Research & 6 days & Mon 10/16/23 & Mon 10/23/23 & \\ \hline & Compare part prices & 2 days & Mon 10/16/23 & Tue 10/17/23 & \\ \hline & \begin{tabular}{l} Review current patents/similar \\ products \end{tabular} & 2 days & Wed 10/18/23 & Thu 10/19/23 & 2 \\ \hline & Feasibility & 2 days & Fri 10/20/23 & Mon 10/23/23 & 2,3 \\ \hline & Product Description & 2 days & Fri 10/20/23 & Mon 10/23/23 & 2,3 \\ \hline & Design & 20 days & Tue 10/24/23 & Mon 11/20/23 & \\ \hline & Create drawing & 7 days & Tue 10/24/23 & Wed 11/1/23 & 5 \\ \hline & Create initial BOM & 5 days & Thu 11/2/23 & Wed 11/8/23 & 7 \\ \hline & Cost Estimate & 4 days & Thu 11/9/23 & Tue 11/14/23 & 7,8 \\ \hline & Communication plan & 4 days & Wed 11/15/23 & Mon 11/20/23 & 7,8,9 \\ \hline & Development & 15 days & Tue 11/21/23 & Mon 12/11/23 & \\ \hline & Create circuit & 4 days & Tue 11/21/23 & Fri 11/24/23 & 10 \\ \hline & 3D Print Prototype case & 4 days & Mon 11/27/23 & Thu 11/30/23 & 12 \\ \hline & Test Air Nobel Pro & 4 days & Fri 12/1/23 & Wed 12/6/23 & 12,13 \\ \hline & \begin{tabular}{l} Documentation for presenting \\ protype \end{tabular} & 3 days & Thu 12/7/23 & Mon 12/11/23 & 12,13,14 \\ \hline^ & Break & 24 days & Wed 12/13/23 & Mon 1/15/24 & \\ \hline & Winter break & 24 days & Wed 12/13/23 & Mon 1/15/24 & 15 \\ \hline & Adjustments & 28 days & Tue 1/16/24 & Thu 2/22/24 & \\ \hline & Cost adjustment & 7 days & Tue 1/16/24 & Wed 1/24/24 & 17 \\ \hline & Identify risks & 7 days & Thu 1/25/24 & Fri 2/2/24 & 19 \\ \hline & Change management plan & 7 days & Mon 2/5/24 & Tue 2/13/24 & 20,19 \\ \hline & Design Adjustment & 7 days & Wed 2/14/24 & Thu 2/22/24 & 21 \\ \hline & Finalize Product & 24 days & Fri 2/23/24 & Wed 3/27/24 & \\ \hline & Fianlize BOM & 7 days & Fri 2/23/24 & Mon 3/4/24 & 22 \\ \hline & \begin{tabular}{l} Create final version of Air Nobel \\ Pro \end{tabular} & 10 days & Tue 3/5/24 & Mon 3/18/24 & 24 \\ \hline & Production Cost Estimate & 7 days & Tue 3/19/24 & Wed 3/27/24 & 24,25 \\ \hline & Advertising Air Nobel Pro & 24 days & Thu 3/28/24 & Tue 4/30/24 & \\ \hline & Create rules and regulations & 7 days & Thu 3/28/24 & Fri 4/5/24 & 26 \\ \hline & Create Brochures & 7 days & Mon 4/8/24 & Tue 4/16/24 & 28 \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts