Question: please do C. do not just do A and B and ignore C. 4. The daily demand for parts made at machining workcell JMB is

please do C. do not just do A and B and ignore C.
please do C. do not just do A and B and ignore C.
4. The daily demand for parts made at machining workcell JMB is 1600 units. The average process- ing time is 25 seconds per unit. A container spends, on average, six hours waiting at JMB before it is processed. Each container holds 250 parts. Currently 10 containers are being used for the part. a. What percent safety margin of stock is being carried? b. If you wanted to retain this safety margin, but remove one container, to what value mus the waiting time be reduced? c. What would happen if the demand for parts increased to 1900 with K=10? 11

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!