Question: please elaborate in written do not show it in the diagram Find the critical path for the following process flow diagram. (Write Pathway and Total

please elaborate in written do not show it in the diagram please elaborate in written do not show it in the
Find the critical path for the following process flow diagram. (Write Pathway and Total Time of Path) Task D 2 Days Task E 4 Days Task F 1 Day Task A 3 Days Start Finish Task B 4 Days Task C 3 Days Your answer ! This is a required