Question: Please explain how to get each number in the worksheet 4.17. Complete the following MRP record. The lead time is 4 weeks, and the lot

Please explain how to get each number in the worksheet
4.17. Complete the following MRP record. The lead time is 4 weeks, and the lot size is 200. What will happen if the gross requirements in week 3 are increased to 150 units? As a planner, what actions can you take? Revised MRP