Question: PLEASE USE EXCEL AND SHOW FORMULAS. THANK YOU! 4.17. Complete the following MRP record. The lead time is 4 weeks, and the lot size is

PLEASE USE EXCEL AND SHOW FORMULAS. THANK YOU!

4.17. Complete the following MRP record. The lead time is 4 weeks, and the lot size is 200. What will happen if the gross requirements in week 3 are increased to 150 units? As a planner, what actions can you take?

PLEASE USE EXCEL AND SHOW FORMULAS. THANK YOU!

Initial MRP [ Revised MRP