Question: please explain. show work 3. Project Crashing A. Compute the per day costs for crashing each activity Normal Crashed Per Day Crashed Cost Activity DurationCost

please explain. show work
3. Project Crashing A. Compute the per day costs for crashing each activity Normal Crashed Per Day Crashed Cost Activity DurationCost Duration |Cost ays $1,000 3 days $2,000 B 5 days$2,5003 days $5,000 2 days $1,200 D 7 days$3,5005 days $5,000 1 day $2,000 F 5 days $2,0004 days $3,000 G9 days$4,5007 days$6,300 A 4 C3 days$750 E2 days$500 3 days B. What is the most attractive candidate to crash: C. What is the second most attractive candidate to crash: D. What is the least attractive candidate to crash