Question: Please explain the Early Start / Late Start and Early Finish / Late Finish calculations and answers. thank you! The following activities constitute a store

Please explain the Early Start / Late Start and Early Finish / Late Finish calculations and answers. thank you!
The following activities constitute a store opening project. Draw the network diagram, find the Early Start/Late Start and Early Finish/Late Finish times for each activity, the critical path, and slack times for all activities. Activity A B D E F Time (weeks) 2. 4 3 5 4 3 Predecessors none A A B B.C DEStep by Step Solution
There are 3 Steps involved in it