Question: please explain with explanation so i can understand better and show formulas ! Consider the following mutually exclusive projects: T=0 Project X: -100 20 Project
Consider the following mutually exclusive projects: T=0 Project X: -100 20 Project Y: -100 80 2 30 30 3 90 20 a. Find IRRs for both projects. b. Find the cross-over rate. c. Construct a graph, where you will show the NPV of each project as a function of its discount rate (ie NPV on the vertical axis and r on the horizontal axis). Both NPVs should be on the same graph. This graph is the NPV schedule. d. Please describe as fully as possible which project is the best and under which circumstances
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts