Question: please fast Consider the following project and prepare an activity schedule which satisfies the resources constraints. If the maximum labour available on any day is

please fast Consider the following project andplease fast
Consider the following project and prepare an activity schedule which satisfies the resources constraints. If the maximum labour available on any day is only 6, Find the EF for activity E Duration Activity A B No. of men req. per day 4. 6 2 3 8 4 6 3 1 to 2 1 to 3 1 to 4 2 to 6 3 to 5 5 to 6 4 to 6 C D 07NW W 0 E 1 F 1 G 1 Select one: O a. 15 O b. 16 O c. 14 O d. 10