Question: Please fill the blanks. critical path will be double. earliest time start(EST), finish time(EFT), Latest time start (LST), Latest time finish (LFT) Total float (TF)
Please fill the blanks.
critical path will be double.
earliest time start(EST), finish time(EFT), Latest time start (LST), Latest time finish (LFT)
Total float (TF)
Free float (FF)
| activity | predecessors | duration (days) |
| A | - | 6 |
| B | - | 7 |
| C | A | 6 |
| D | A | 4 |
| E | B, C | 7 |
| F | B, C | 8 |
| G | D, E | 6 |
| H | F | 5 |
| activity | working time |
| ||||
| EST | EFT | LST | LFT | TF | FF | |
| A |
|
|
|
|
|
|
| B |
|
|
|
|
|
|
| C |
|
|
|
|
|
|
| D |
|
|
|
|
|
|
| E |
|
|
|
|
|
|
| F |
|
|
|
|
|
|
| G |
|
|
|
|
|
|
| H |
|
|
|
|
|
|
|
|
|
Thanks in advance!
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
