Question: Please fill the blanks. critical path will be double. earliest time start(EST), finish time(EFT), Latest time start (LST), Latest time finish (LFT) Total float (TF)

Please fill the blanks.

critical path will be double.

earliest time start(EST), finish time(EFT), Latest time start (LST), Latest time finish (LFT)

Total float (TF)

Free float (FF)

activity

predecessors

duration

(days)

A

-

6

B

-

7

C

A

6

D

A

4

E

B, C

7

F

B, C

8

G

D, E

6

H

F

5

activity

working time

EST

EFT

LST

LFT

TF

FF

A

B

C

D

E

F

G

H

Thanks in advance!