Roger Ginde is developing a program in supply chain management certification for managers Ginde has listed a number of activities that must be compi conducted. The activities immediate predecessors, and times appear in the accompanying lable
\table[[Activity,Immediate Predecessor(s),Time (days)],[A,-,2],[B,-,5],[C,-,3],[D,B D,10],[E,C,3],[F,E. F,5],[G,,10]]
This exercise contains only parts b c, and d
b) The critical activities for the leadership training program development project are B-D E ,G
c) The project length for the leadership training program development project =28 days
d) Slack time for each of the activities is
 PLEASE FIND SLACK TIME FOR A,B,C,D,E,F,G I'LL GIVE YOU A THUMBS

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!