Question: PLEASE FIND SLACK TIME FOR A , B , C , D , E , F , G I'LL GIVE YOU A THUMBS UP Roger
PLEASE FIND SLACK TIME FOR ABCDEFG
I'LL GIVE YOU A THUMBS UP
Roger Ginde is developing a program in supply chain management certification for managers Ginde has listed a number of activities that must be compi conducted. The activities immediate predecessors, and times appear in the accompanying lable
tableActivityImmediate PredecessorsTime daysABCDB DECFE FG
This exercise contains only parts b c and d
b The critical activities for the leadership training program development project are BD E
c The project length for the leadership training program development project days
d Slack time for each of the activities is
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock