Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activity Immediate Predecessor(s) Time (days) A ..................... - .................................... 2 B .........................-................................. 7 C ...................... - ....................................1 D ...................... B .............................. 10 E ......................A, D ............................ 3 F ..................... C ............................... 5 G ................... E, F ............................ 10

This exercise contains only parts b, c, and d.

b) The critical activities for the leadership training program development project are

B - D - E - G

.

c) The project length for the leadership training program development project =

3030

days.

d) Slack time for each of the activities is:

Activity

Slack Time

A

0

B.

C

D

E

F

G

please provide formula to learn

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!