Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity Immediate Predecessor(s) Time (days) A ..................... - .................................... 2 B .........................-................................. 7 C ...................... - ....................................1 D ...................... B .............................. 10 E ......................A, D ............................ 3 F ..................... C ............................... 5 G ................... E, F ............................ 10
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are
B - D - E - G
.
c) The project length for the leadership training program development project =
3030
days.
d) Slack time for each of the activities is:
| Activity | Slack Time |
| A | 0 |
B.
C
D
E
F
G