Question: Please give the correct answer and calculation process Hours per week 40 Labor cost per hour $15 Material cost $3 per meter Overhead cost 20%
Please give the correct answer and calculation process
Hours per week 40
Labor cost per hour $15
Material cost $3 per meter
Overhead cost 20% of weekly labor
Weekly Output (items) Number of Workers Material (meters)
4520 12 3497
5,520 17 3943
3,700 10 2467
What is the multifactor productivity item per dollar for week 1? (Round it to 2 decimal places.)
What is the multifactor productivity item per dollar for week 2? (Round it to 2 decimal places.)
What is the multifactor productivity item per dollar for week 3? (Round it to 2 decimal places.)
What is the multifactor productivity ($ output per $ input) for week 1? (Round it to 2 decimal places.)
What is the multifactor productivity ($ output per $ input) for week 2? (Round it to 2 decimal places.)
What is the multifactor productivity ($ output per $ input) for week 3? (Round it to 2 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts