Question: please help due soon During 2021, Blossom Corp. started a construction job with a total contract price of $14500000. The job was completed on December
please help due soon
During 2021, Blossom Corp. started a construction job with a total contract price of $14500000. The job was completed on December 15, 2022. Additional data are as follows: Under the completed-contract method, what amount should Biossom recognize as gross proft for 2022? $1150000$2050000$250000$575000