8.) Consider the following projects:
| PROJECT | CASH FLOWS ($) C0 | C1 |
| D | -11,800 | 23,600 |
| E | -21,800 | 38,150 |
Assume that the projects are mutually exclusive and that the opportunity cost of capital is 9%. a. Calculate the profitability index for each project. (Do not round intermediate calculations. Round your answers to 2 decimal places.)
| PROJECT | profitability index |
| D | |
| E |
b-1. Calculate the profitability-index using the incremental cash flows. (Do not round intermediate calculations. Round your answer to 2 decimal places.)
profitability index =__________
b-2. Which project should you choose? A. PROJECT D
B.PROJECT E
PLEASE SHOW ALL WORK. THIS SAME QUESTION HAVE BEEN POSTED ON CHEGG MANY TIMES BUT THE ANSWERS ARE ALL WRONG., I SUBMITTED THOSE ANSWER AND IT WAS MARKED WRONG. THE ANSWER IS NOT 1.83, 1.61 ,1.33. PLEASE GIVE ME THE RIGHT ANSWER. THANK YOU
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts