Question: Please help! I will give you a good rating! :) 1) The task Determine Requirements is a 10-day task. Expenditures/day are set at $2,000. Day
Please help! I will give you a good rating! :)
1) The task Determine Requirements is a 10-day task. Expenditures/day are set at $2,000. Day 5 is just completed. If the SPI is .48, the BCWP ________. (Hint: SPI = EV/PV)
a. $4,800
b. is the same as the PV
c. is $8000
d. depends on the AC
e. none of these
2) The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. What is the PV?
a. $12,000
b. $10,000
c. $9,000
d. $5,000
e. $3,000
3) The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. What is the budgeted cost of this task?
a.$15,000
b.$12,000
c.$9,000
d.$5,000
e.$3,000
4) The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. Assume the percent complete is 25%. What is the EV?
a. $6000
b. $12,000
c. $4000
d. $2500
e. $3000
5) The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. Assume the percent complete is 25%. What is the schedule variance, SV?
a. $2000
b. $3000
c. -$3000
d. -$2000
e. $0