Question: Please help! I will give you a good rating! :) 1) The task Determine Requirements is a 10-day task. Expenditures/day are set at $2,000. Day

Please help! I will give you a good rating! :)

1) The task Determine Requirements is a 10-day task. Expenditures/day are set at $2,000. Day 5 is just completed. If the SPI is .48, the BCWP ________. (Hint: SPI = EV/PV)

a. $4,800

b. is the same as the PV

c. is $8000

d. depends on the AC

e. none of these

2) The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. What is the PV?

a. $12,000

b. $10,000

c. $9,000

d. $5,000

e. $3,000

3) The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. What is the budgeted cost of this task?

a.$15,000

b.$12,000

c.$9,000

d.$5,000

e.$3,000

4) The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. Assume the percent complete is 25%. What is the EV?

a. $6000

b. $12,000

c. $4000

d. $2500

e. $3000

5) The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. Assume the percent complete is 25%. What is the schedule variance, SV?

a. $2000

b. $3000

c. -$3000

d. -$2000

e. $0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!