Question: Please help! I will give you a good rating! :) There are questions that are refer to the table below! 1) The following sequence of

Please help! I will give you a good rating! :) There are questions that are refer to the table below!

Please help! I will give you a good rating! :)

1) The following sequence of tasks is planned for a project. The project is 17 days old. What tasks are currently being worked on assuming early starts on all tasks?

a. C and E

b. C and D

c. D and E

d. D and F

e. D and F

2) The following sequence of tasks is planned for a project. The project is 17 days old. What is the PV for task B assuming an early start?

a. $12,000

b. simply the budgeted cost of the work scheduled, BCWS

c. both a. and b. are correct

d. Simply the budget cost of work performed, BCWP

e. both a. and c. are correct

3) The following sequence of tasks is planned for a project. The project is 17 days old. What is the PV for task D assuming an early start?

a. $3000

b. $9000

c. $0

d. $12,000

e. $6000

4) The following sequence of tasks is planned for a project. The project is 17 days old. What is the PV for task C assuming an early start?

a. $9000

b. $10,000

c. $8000

d. $7000

e. $0

5) The following sequence of tasks is planned for a project. The project is 17 days old. What is the PV for task E assuming an early start?

a. $12,000

b. $10,000

c. $14,000

d. $6,000

e. $0

6) The following sequence of tasks is planned for a project. The project is 17 days old. What is the PV for task F assuming an early start?

a. $0

b. $3,000

c. $12,000

d. $2,000

e. $6000

7) The following sequence of tasks is planned for a project. The project is 17 days old. The budgeted cost of task C is ________ and of task E is ________.

a.

$6,000 | $20,000

b.

$12,000 | $14,000

c.

$10,000 | $14,000

d.

$10,000 | $12,000

e.

$24,000 | $6,000

8) The following sequence of tasks is planned for a project. The project is 17 days old. Assume task D is 40% done. What is the schedule variance? Recall that schedule variance is SV = EV PV.

a. -$4000

b. $4000

c. $-3000

d. $3000

e. $3600

9) The following sequence of tasks is planned for a project. The project is 17 days old. Assume task E is 30% done. What is the schedule variance for task E, assuming an early start? Recall that schedule variance is SV = EV PV.

a. $2000

b. -$7800

c. $7200

d. -$7200

e. $7800

10) The following sequence of tasks is planned for a project. The project is 17 days old. Assume the AC for task E is $11,600. The task is 80% done. What is the cost variance CV for task E assuming an early start? Recall that cost variance is CV = EV AC.

a. $0

b. -$400

c. $400

d. $2000

e. -$2000

Task Predecessor(s) | Duration (Days) Cost per Day $1,000 $2,000 $1,000 $3,000 $2,000 D, E $1,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!