Answer these questions for the following simple set of project tasks. Task times are shown in hours 3 B 2 C 6 D 6 E 4 H 3 F 7 G 6 a. What is the length of the critical path? Length of the critical path hours b. What are the earliest start and latest start for E? Earliest start thd hour Latest start thd hour c. What is the latest start for B? Latest start thd hour