Question: PLEASE HELP NAME DURATION Predecessor A 3 B. 4 2 A,B D 6 E 7 F. 4 G 7 DE H 3 F I 7

PLEASE HELP

PLEASE HELP NAME DURATION Predecessor A 3 B. 4 2

NAME DURATION Predecessor A 3 B. 4 2 A,B D 6 E 7 F. 4 G 7 DE H 3 F I 7 F Above is the activity table of the project. For the given project, find the critical path and the project duration. O A-C-D-H-I, 21 O B-C-F-E, 18 O B-C-E-G, 20 O None of the above A-B-C-F-H-I, 22